Lift panel at angle through grid.
Drop ceiling grid installation instructions.
Don t assume the wall is straight.
A b step install panels 3 2 x 2 installation 1.
Screw an eyelet into every.
If the grid is not square shorten one of the main beams until the diagonals are equal.
Measure across the diagonals of the 2 x 4 opening.
Trim border panels cutting panel face side up b.
Check the original sketch of the room to determine this location.
Join sections of main beam.
Secure the end of a chalk line on one end of.
Typical installation tee patterns 2 x 4 grid layout 2 x 4 tee layout 2 x 2 tee layout planning for 2 x 2 ceiling panels.
Cut the main tees for the drop ceiling hangers.
Suspended ceiling for 2 x 4 ceiling panels.
The cross tee slots must line up.
Locate the first suspension wire for each main tee directly above the point where the first cross tee meets the main tee.
Once you ve figured out the size of the border row measure back from the cross tee slots and cut your main tees to size.
Installation of hangers ceiling soffit duct section threaded rod hanger wire vertical support slotted bar main tee for suspending the ceiling.
Apply them to the ceiling with screw eyes screw hooks nails or by drilling.
Putting in the grid system 1.
Measure and cut the main tees according to a cross tee guideline.
Install wall molding mark the desired new ceiling height on the wall.
Determine the size of your border panels from side to side.
Install hanger wire or.
Snap the chalk line tool to create this.
Then layout your tile spacing and see how it looks.
Step 1 design your drop ceiling grid it starts with a game plan.
Slope 1 in 1 8mtr in any plane if more use counter splaying wires step 5.
The measurements will be the same if the grid is square.
Hanger wire can be suspended for ceiling installation.
Be sure the suspension wires are securely fastened.
To allow for ceiling tile installation and accessibility the minimum drop is 3 with traditional hanger wire or 2 5 with quickhang grid hooks.
Additional 2 cross tees dotted lines are installed parallel to the main tees 2 o c.
The main runners will support the.
Literally measure and make a to scale drawing of each room.
Installing 2 x 4 drop ceiling panels determine the size of the border panels to get the length of your border panels divide the width of the room by the.
Install two four foot cross tees between the two main beams in line with the first two border cross tees.
If you are using 2 x 2 panels you need to lay out your grid differently.
Cut the main runners to fit the length of your room perpendicular to the joists.
Three easy steps to install your ceiling 1.
300mm 45 0 45 0 300mm 1 80mtr.